Shelters substandard, too
By Fernando del MundoPhilippine Daily Inquirer
The construction of bunkhouses as
temporary shelters for families of homeless typhoon victims has raised
questions about the direction and integrity of the government’s
rehabilitation and recovery program.
Allegations of overpricing and substandard
work have raised fears that the entrenched pork barrel system that
spawned the alleged P10-billion Janet Lim-Napoles racket exposed by
whistle-blowers last July is again rearing its ugly head in this early
stage of reconstruction following the most violent typhoon to hit this
country.
At least 203 bunkhouses—each unit divided
into 24 rooms that would house as many families—are being built in more
than a dozen towns in Leyte and Eastern Samar, according to the
Department of Public Works and Highways (DPWH).
Each room measures 8.64 square
meters—roughly the size of two Ping-Pong tables—to be occupied by one
family, said a DPWH paper, “shelter and reconstruction action plan.” The
average size of a Filipino family is five, but in many cases there are
as many as 10 individuals in one household.
A report by an international shelter group
assisting the government in its relief efforts said the bunkhouses being
developed by the DPWH in areas devastated by Supertyphoon “Yolanda”
(international name: Haiyan) were “noncompliant in many respects with
internationally recognized standards and best practices.”
“There appears to be a number of
contractors working at different sites. Standards and facilities appear
to be somewhat different between different locations. It raises the
question of whether contractors have different specifications for
different sites, if they are using the same specifications, whether
these are fully complied with in every location,” said the report made
available to the Inquirer.
Other concerns
The report by the Camp Coordination and
Camp Management (CCCM) group raised concerns ranging from cramped spaces
to lack of ventilation, risk of fires and safety and security of
occupants.
Field officers of the CCCM, involved in
shelter programs in countries wracked by civil strife and natural
calamities, have quietly discussed with municipal authorities
apprehensions at the lack of privacy in rooms separated by thin plywood
walls and sexual molestation of children while their parents are away
trying to eke out a living.
At the very least, consultations with the potential occupants have been suggested.
While “protection issues” are the main
concerns of the international workers, local authorities are worried
about the potential for corruption in the government’s reconstruction
and recovery initiatives in the ruined communities.
One issue is the soundness of constructing
temporary quarters nearly two months after Yolanda struck on Nov. 8,
after the emergency had passed, rather than getting people back on their
feet and building permanent shelters instead.
The most powerful storm to make landfall in
history killed more than 6,100 people with winds of 315 kilometers per
hour and tsunami-like storm surges, affected 14 million people, and made
homeless 4 million of them.
Providing permanent shelters, along with
livelihood, is an important first stage in the reconstruction, according
to experts interviewed by the Inquirer.
The 15-page CCCM cluster report could be
telling. Politicians and priests in Leyte and Samar are worried about
reports that a 24-room bunkhouse is being constructed at a cost roughly
below P200,000 and not P959,360—the price tag put on it in the DPWH
plan.
Specs not followed
The nearly P1-million expense in the DPWH
“individual program of work” for each of the 11 bunkhouses now
undergoing construction in Tacloban City, for example, includes such
amenities as four toilets, two bathrooms and a common kitchen.
In at least one municipality in Eastern Samar, however, some of the bunkhouses do not have toilets, baths or kitchen.
A report by the municipal engineer of this
town, sent to former Sen. Panfilo Lacson, point man of the Aquino
administration’s rehabilitation efforts, detailed failures of private
contractors of the DPWH to comply with specifications of the department.
For example, this engineer said that while
the DPWH specification on roofing was 0.50 millimeter, a 0.30 mm or 0.40
mm sheet was used in some of the bunkhouses; a 6 mm thick plywood wall
specified was replaced with a thinner 3/16; instead of a 3/4 plywood for
flooring, a 1/2 plyboard was employed.
A government engineer in Manila said in a
cost estimate that without the toilets, baths and kitchen and simply
coming up with the dwelling, direct cost using coco lumber, ordinary
plywood and GI sheets would be P170,075.
Add a 10-percent profit margin of P17,007
and 12-percent overhead cost contingency and miscellaneous expenses and
the total comes up to P232,391. Each room in this estimate can be built
for P19,365.94.
A simple thatched hut could be built with this amount, according to experts.
Both engineers spoke on condition of anonymity because they had no authority to talk to reporters.
Faithful compliance
Rolando Asis, DPWH director for Eastern
Visayas, insisted in an interview in Tacloban that the department’s
specifications were being complied with faithfully and that mayors had
agreed to the project, especially for informal settlers.
He said that bunkhouses were being built by
private contractors outside the affected region and that the costs were
in fact lower. He said a similar shelter for victims of Tropical Storm
“Sendong” (international name: Washi) in Mindanao two years ago cost
P1.2 million.
“They’re just breaking even,” Asis said,
pointing out that materials were coming from outside the affected
region—from Manila, Davao and Cebu—and that this accounted for the high
expense. He said even laborers were being imported. “They are just
trying to help.”
In one Eastern Samar town, however, the
Inquirer has learned that at least six private contractors were local
residents. One of them is an officer of the Commission on Elections who
did not have the capacity to cough up the P1-million investment for a
single bunkhouse project. The six are neither engineers nor contractors.
The Inquirer was told that the contractors
were recommended by an administration politician and that their
selection stemmed from traditional practice in the lawmakers’ pork
barrel system—the Priority Development Assistance Fund—that has been
roundly condemned following allegations that funds meant to ease rural
poverty had been diverted to ghost projects and kickbacks. This meant
the DPWH contractors needed the blessing of the local political kingpin.
One town mayor, who likewise spoke on
condition of anonymity for fear of being left out in the reconstruction
process, said he had not been told how long the temporary structures
would remain and when permanent shelters would be built.
The selection of relocation sites is a
major problem. The government has announced that construction of houses
will not be allowed within 40 meters of the coastline, reckoned at high
tide.
That would require national legislation
given the vulnerability of coastlines to violent storms in the era of
climate change. In some towns, impatient mayors are pushing ordinances
to enforce no-build zones.
Not pigs in a pen
Management of the bunkhouse sites could be a
major problem at the turnover by the private contractors, unless
ironclad guarantees are arranged for the security and well-being of the
occupants.
“It’s not a simple case of dumping pigs in a pen,” the mayor said.
For some people uprooted, like Ailyn Ambid,
25, anything anywhere is better than the ramshackle hut where she is
staying at Barangay 88, near the Tacloban airport. There, she lost her
husband and three children to Yolanda.
“This place has many bad memories. I would
rather move out and get on with my life,” she said, adding that she had
no qualms moving to the bunkhouse in the city.
Francisco Bandaje Jr., a 35-year-old father
of seven, would rather stay and rebuild his home at the barangay. He
works as a driver at the airport.
Disclosure of potential irregularities
comes amid a request by the United Nations for a $791-million assistance
for the government’s rehabilitation and recovery plan for the
Yolanda-wrecked regions.
While Public Works Secretary Rogelio
Singson has impeccable credentials as a clean and honest manager,
concerned municipalities are worried that he may not be aware of what is
happening on the ground.
Calls for transparency have been aired by
ambassadors of donor countries. Last month, the envoys went on a tour of
the typhoon-affected areas, accompanied by Social Welfare Secretary
Corazon “Dinky” Soliman and the UN humanitarian coordinator in the
Philippines Luisa Carvalho.
At the end of the tour in Ormoc City,
Ambassador Neil Reeder of Canada, echoing the sentiments of the
diplomats, said: “The next six months into the new year is a very
critical window as you transition into the reconstruction phase beyond
the immediate needs … . We want to have an open, transparent process.”
No comments:
Post a Comment